UNIT N Research / 2026 Edition

Transparent Renovation Cost Index

A city guide for homeowners who want to see what they can budget upfront and what delays or rework could cost them.

01 / Local permit fees

One renovation example, three cities

Vereniging Eigen Huis calculated municipal permit fees for an example renovation with €80,000 in construction costs excluding VAT. Design review and other charges can come on top. Use the figures for comparison and check how the council would assess your own plans.

What the fee comparison covers

The Hague

The comparison uses the same example construction budget in both years. Any charges for scaffolding or a skip in public space are separate.

2025 in the same survey€3,392

02 / National price examples

What does the price include?

These Dutch guide prices come from Vereniging Eigen Huis market research at 2027 price levels. Use them to clarify the scope of your quote. The sources reviewed here lack city averages for completed home renovations.

Bathroom · 6 m²

€8,270

Standard specification including VAT and installation. Removing the existing bathroom is excluded.

Kitchen · standard

€7,005 – €15,200

Branded kitchen with standard appliances, including VAT. Confirm installation and budget separately for removal and moving services.

Extension shell · 15 m²

€35,545 – €45,490

Including VAT. Opening the existing wall, finishes, services and fit-out are excluded.

03 / Scenario calculator

What would a delay cost you?

Compare two budgets for the same renovation. Enter the additional weeks, weekly expenses and rework you expect. Use the same VAT basis for all amounts.

Editable example

Examples include temporary accommodation, storage and longer equipment hire. Count each expense once.

Decide during construction
Resolve before construction

The model adds delay × weekly costs, rework and any extra preparation. The common construction budget is excluded. The default inputs illustrate the calculation. For example, include extra temporary accommodation if a late delivery shifts handover. Include only work that must be done again under rework.

04 / Sources and method

What we want to measure next year

A credible city average needs comparable completed projects. Group them by city, property type, scope, floor area and finish level. For each project, record the agreed construction budget, final bill, VAT, planned and actual handover, and reasons for additional work.

Publish the number of projects, the median and the middle half of observations for each comparable group. Keep quote, permit and final bill figures separate. Leave out small groups and compare planning approaches once there are enough comparable projects.

Proposed annual update · fixed November cut-off. Keep each edition with its original pricing basis and publication date.